Charlotte’s Mews – Construction Update:

Publish Date: 15 Nov 2017

Charlotte Nov

Great progress has been made on-site with this project, particularly in regards to external finishes. The application of rear units’ external cladding is almost complete whilst the front units have had their ground floor brickwork finalised and first floor prepared for cladding.


Publish Date: 9 Oct 2017

Charlotte Sept Watermarked

This project is coming along nicely with roofing nearly complete and window installation in progress. Service rough in works are also well-underway, great to see.


Publish Date: 28 Aug 2017

Charlotte Aug

Framing has been completed for most units on site. The brickwork on rear units has also commenced. This project is really starting to take shape!


Publish Date: 28 July 2017

charlotte july watermarked

The steelwork for this project is complete with timber framing continuing to go up on site. The rough in works, particularly for NBN services, have also begun on site. This project is really starting to come together!


Publish Date: 30 June 2017

Charlotte June

We've had a bumper few weeks out at Charlotte's Mews! All slabs are now poured, steelwork is underway and the first floor timber framing is being installed in the rear townhouses. It's all full steam ahead at Charlotte's Mews!


Publish Date: 31 May 2017

Charlotte watermarked

Slabs are going down! Some very exciting news for this project!


Publish Date: 3 May 2017

Adele

Preparations are taking place on site for the slab to be poured next week! We are very excited to this project advancing!