Construction News

Gabrielle's Gardens - Construction Update:

Publish date: 15 Nov 2017

Gabrielle Nov

This project’s internal fit-out is almost finished, with kitchen joinery and appliances installed and bathroom installation progressing towards completion. External finishes have also advanced as cladding has been completed. Additionally, the driveway has been completed with landscaping works to begin shortly.


Charlotte's Mews - Construction Update:

Publish date: 15 Nov 2017

Charlotte Nov

Great progress has been made on-site with this project, particularly in regards to external finishes. The application of rear units’ external cladding is almost complete whilst the front units have had their ground floor brickwork finalised and first floor prepared for cladding.


Xavier’s Rise - Construction Update:

Publish date: 15 Nov 2017

Xavier Nov

This project is nearing practical completion as kitchen and bathroom joinery and appliance installation is well underway. External site preparation has also been undertaken, which allows for landscaping and concreting to begin.


The Belle Apartments – Construction Update:

Publish date: 15 Nov 2017

Belle Nov

This project’s internal fit out is advancing further with kitchen installation in progress whilst the application of external finishes is well underway. The rear and sides of the project have had their cladding and brickwork rendering completed, with the front façade finishes to be applied shortly.


Rye Beach Homes - Construction Update:

Publish date: 24 Oct 2017

1 Hyg

It’s our absolute pleasure to announce that Dovetail’s first project in our new Bayside Born series has begun! Our Rye Beach Homes have commenced construction over the past week, with the site marked out and prepared for ground works to begin. The Dovetail Team is very excited to see the hard work put into planning process finally start to come into fruition. We’ll be sure to keep you updated on Dovetail Development’s next chapter, as our Bayside adventures unfold.


Gabrielle's Gardens - Construction Update:

Publish date: 9 Oct 2017

Gabrielle Sept watermarked

White goods & service fit out has commenced for this project, whilst internal painting is nearing completion with final ceiling coats applied and final wall coats also commencing. It’s also very exciting to see that preparations for site external works, such as landscaping and paving, are in progress.


Charlotte's Mews - Construction Update:

Publish date: 9 Oct 2017

Charlotte Sept Watermarked

This project is coming along nicely with roofing nearly complete and window installation in progress. Service rough in works are also well-underway, great to see.


Xavier’s Rise - Construction Update:

Publish date: 9 Oct 2017

Xavier Sept watermarked

Much progress has been made on this project regarding the internal fit out. Internal carpentry is almost complete, painting is well underway and kitchen installation is nearing completion.


The Belle Apartments – Construction Update:

Publish date: 9 Oct 2017

Belle Sept watermarked

Internal fit out is underway, with kitchen installation in progress, and white goods & services fit out commencing. Painting is also nearing completion as walls are ready for final coats. Very exciting!


Gabrielle's Gardens - Construction Update:

Publish date: 28 Aug 2017

Gabrielle Aug

The roof and roof flashings are complete, along with all timber framing and the brickwork. The rough in of hydraulic and electrical services is also progressing very well. Great job!


Charlotte's Mews - Construction Update:

Publish date: 28 Aug 2017

Charlotte Aug

Framing has been completed for most units on site. The brickwork on rear units has also commenced. This project is really starting to take shape!


Xavier’s Rise - Construction Update:

Publish date: 28 Aug 2017

Xavier Aug

External works are continuing whilst internal works have commenced, with plastering beginning on site.


The Belle Apartments – Construction Update:

Publish date: 28 Aug 2017

Belle Aug

The window and door installation has now been completed on site. In addition, the internal fix-out has commenced with preparations on-going for this stage of construction.


Gabrielle's Gardens - Construction Update:

Publish date: 28 July 2017

gabrielle july watermarked

The roof and roof flashings are complete, along with all timber framing and the brickwork. The rough in of hydraulic and electrical services is also progressing very well. Great job!


Charlotte's Mews - Construction Update:

Publish date: 28 July 2017

charlotte july watermarked

The steelwork for this project is complete with timber framing continuing to go up on site. The rough in works, particularly for NBN services, have also begun on site. This project is really starting to come together!


Xavier’s Rise - Construction Update:

Publish date: 28 July 2017

Xavier July watermarked

The roofworks have been completed, with cladding due to commence. The rough in of services has also started to occur on site. We're exciting to see this project progress further!


The Belle Apartments – Construction Update:

Publish date: 28 July 2017

Belle July watermarked

Roof framing is complete, along with wall framing. Services have also begun to be roughed in. The team is making great time with The Belle!


Gabrielle's Gardens - Construction Update:

Publish date: 30 June 2017

Gabrielle June

Check out the brickwork at Gabrielle's Gardens! You can also picture how those garden beds are going to sit beautifully into the balcony cavities. We have released one final townhouse to the market in this project (which has a truck load of upgrades thrown in) - if you're interested in taking a look, contact Jerry our Sales Agent on 0413 737 778.


Charlotte's Mews - Construction Update:

Publish date: 30 June 2017

Charlotte June

We've had a bumper few weeks out at Charlotte's Mews! All slabs are now poured, steelwork is underway and the first floor timber framing is being installed in the rear townhouses. It's all full steam ahead at Charlotte's Mews!


Xavier’s Rise - Construction Update:

Publish date: 30 June 2017

Xavier June

It may have been a cold, misty morning at Rosella Ave, but works at Xavier's Rise continue to progress along nicely, with the internal fit out underway, windows in and the roof taking shape.


The Belle Apartments – Construction Update:

Publish date: 30 June 2017

Belle June

We're thrilled that all slabs are now poured and level 2 walls are underway. Watch this space, as it will not be long until the roof trusses are installed!


Xavier's Rise – Construction Update:

Publish date: 12 June 2017

xaviers rise

This project is really taking shape! We're also glad someone has been watching over the place this long weekend!


The Belle – Construction Update:

Publish date: 31 May 2017

Belle watermarked

The first level slab has been poured with the walls going up as well! The Belle Apartments are absolutely flying!


Gabrielle's Garden – Construction Update:

Publish date: 31 May 2017

Gabrielle watermarked

The framing has gone up on the ground floor, with the construction of first floor structures on-going. Great to see the brickwork has commenced also!


Charlotte's Mews – Construction Update:

Publish date: 31 May 2017

Charlotte watermarked

Slabs are going down! Some very exciting news for this project!


Xavier's Rise – Construction Update:

Publish date: 3 May 2017

Rosella Watermarked 20170503

The vertical structures are up at Xavier’s Rise. What a difference one week makes!


The Belle – Construction Update:

Publish date: 3 May 2017

Belle

Construction at The Belle is absolutely steaming ahead with great progress made on site. We are very excited to see this project take shape! There’s still an opportunity to begin the next chapter of your life with a brand new home in The Belle – visit TheBelle.com.au for more details!


Charlotte's Mews – Construction Update:

Publish date: 3 May 2017

Adele

Preparations are taking place on site for the slab to be poured next week! We are very excited to this project advancing!


Xavier's Rise – Construction Update:

Publish date: 27 April 2017

xavier

It is great to see our project on Rosella Avenue continue to advance. Slabs have now been poured and we are ready for the next stage of construction!


The Belle – Construction Update:

Publish date: 15 April 2017

thebelle

Hot off the press and just in time for Easter! Construction of the Belle Apartment complex is progressing rapidly, with slabs poured and vertical structures starting to go up! We’re excited to see this dream become a reality - visit TheBelle.com.au for more information on how you can live the dream.